Citation Codes: 2025 SCC OnLine SC 24
Date of Judgement: 03 January 2025
Court: Supreme Court of India
Coram: Justice P. S. Narsimha and Justice Sandeep Mehta
Factual Background
The case revolves around the inception of limitation period for filing objections to an arbitral award under the Arbitration Act, 1940 (“The Act”) between M/S S.R. Engineering Constructions (“Appellant”) and Union of India and other concerned departments (“Respondents”).
Background of dispute
Appellant secured a work order from Respondents in 1987-88 to construct a permanent ‘armament section’ at Tezpur. Upon completion of the work, the Respondents failed to make the due payment, compelling the Appellant to resort to arbitration mechanism. Despite several unsuccessful attempts to appoint an arbitrator, the Appellant’s application under Section 20 was eventually allowed by District Judge, Sonitpur, on 26.08.2019.
Arbitral Award
An award dated 31.05.2022 was made in favour of the Appellant directing the Respondents to pay a sum of Rs. 1,33,47,268.92/- with an interest of 9% p.a. till realization. Since the Respondents did not clear their dues towards the arbitrator’s fee, the award could not be made, prompting the Appellant to file an application under Section 38 of the Act. On 21.09.2022 the District Judge directed the Respondents to clear the due so that copy of the award could be furnished to both parties.
The Appellant received the copy of the award on 22.09.2022, but the Respondents only deposited a cheque for the balance payment on 18.11.2022, after which they received the notice of filing of the award on the same date. Subsequently, on 10.11.2022 the Appellant filed an application under Section 17 of the Act seeking pronouncement of the judgment. Both the District Court and High Court dismissed the said application as premature, observing that the limitation period for filing objections began only on 18.10.2022, when the Respondents received formal notice of the award.
Issue
Whether the time for filing a Section 17 application commences when the party seeking to challenge the award receives a formal notice of the making of the award, or from the date such party is aware of the existence of the award?
Appellant’s Position
The Appellant argued that the limitation period under Article 119(b), Schedule I of the Limitation Act, 1963, commenced on 21.09.2022, when the court directed the Respondents to pay the arbitrator’s balance fee, implying knowledge of the award’s filing. Since no objections were raised within 30 days, the Appellant filed a Section 17 application. The Respondents did not deny having received notice of the award’s filing, only the copy of the award itself. The Appellant emphasized that Section 14(2) Act only requires awareness of the award’s filing, not formal written notice. Citing Nilkantha Sidramappa Ningashetti v. Kashinath Somanna Ningashetti, Deo Narain Choudhury v. Shree Narain Choudhury, and Ch. Ramalinga Reddy v. Superintending Engineer, they asserted that oral or informal communication suffices, and the court’s order was adequate to inform the Respondents of the award.
Respondent’s Position
On the contrary, the Respondents contended that Section 14(2) requires strict compliance through formal notice of the award and mere direction to pay arbitrator’s fees cannot substitute for this requirement. The intent behind the provision is to enable the award-debtor to apprise himself of the contents for effectively filing objections, if any. Therefore, mere communication of the award’s existence cannot be considered as sufficient compliance and would render it otiose.
Nonetheless, the order dated 21.09.2022 merely directed payment of arbitrator’s fees before the award would be furnished, implying that fee payment alone didn’t satisfy Section 14(2), which required formal notice. Affirming the argument put forth, a formal notice was issued by the court on 18.11.2022. Also, if Appellant’s interpretation is permitted, the legal event which constitutes as ‘notice of the filing of award’ will vary from case to case, which does not seem to convey the intention behind Section 14(2).
Decision and Reasoning
The Court held that the Respondents had sufficient notice of the filing of award through the order dated 21.09.2022, which directed them to pay the arbitrator’s fees, following which the award shall be furnished. While Article 119(b) of the Limitation Act requires ‘service of notice’ and Section 14(2) of the Act states that the Court should ‘give notice’, the precise form of what constitutes as ‘notice’ is unspecified. The crucial factor is informing parties of the award so that they may file objections if needed, rather than on strict procedural formalities. Otherwise, the parties aware of the award would strategically delay objections undermining the speedy intent governing arbitration.
Furthermore, Section 14(2) requires the parties to be aware of the award, with notice to legal representatives being sufficient; insisting on procedural technicalities would allow unfair delays in filing objections. In support of this, the Court cited Food Corporation of India v. E. Kuttappan and Indian Rayon Corporation Ltd. v. Raunaq and Co. (P) Ltd.
Relying on Bharat Coking Coal Ltd. v C.K. Ahuja, the Court held that the date of receiving a copy of the award is not the requirement of Section 14(2), but merely awareness that it is available to the parties signifying that the parties have to take steps to scrutinise the award themselves as soon as it becomes accessible. A contrary interpretation would permit the award-debtor to use procedural loopholes to delay arbitration.
Ergo, the District Court and High Court erred in treating the Appellant’s Section 17 application as premature. The limitation expired on 20.10.2022 and accepting Respondent’s argument would unjustly reward delay.
Conclusion
This ruling significantly impacts Indian arbitration by affirming that procedural timelines exist to promote fairness, not obstruction. A party aware of an award cannot claim ignorance due to lack of formal notice, as this would allow misuse of technicalities to indefinitely delay the arbitral process. It balances procedural discipline with access to remedies, avoiding injustice from mere formal defects. This clarity ensures litigants and lawyers understand that actual knowledge triggers the obligation to act, reducing intentional delays and aligning India’s arbitration practices with global standards focused on fairness and efficiency.
Author(s)

Aparna Upadhyay
Student at Banaras Hindu University
